Construction Update:

  • Russell Park is temporarily a one-way street with vehicle access toward Hancock Street. The south lane on Russell Park will be closed for vehicle access from Hancock Street on to Russell Park. The one-way TMP on Russell Park will be in place through April of 2023. 

1170 Hancock Street

  • Window installation is now underway
  • Sheetrock installation is expected to start next week
  • Air vapor barrier and window flashing is underway
  • Rooftop equipment delivery, hoisting and installation is starting at the end of the month
  • Mechanical, electrical, and plumbing rough is ongoing

 

 

1200 Hancock Street

  • On-site utility installation is nearing completion
  • Installation of lower garage under-slab plumbing is in progress
  • Elevated slab placement will be complete this month
  • Wood framing installation will be ongoing through March
  • Mechanical, electric and plumbing rough is expected to start late February
  • Exterior light gauge metal framing and sheathing installation is now underway

———-

Project Timeline

May 2022: Demolition of 1200 Hancock St. is now complete
Early Spring 2022: Excavation and foundations at both buildings ongoing through the summer of 2022
Early 2024: The project is expected to be complete

———-

Once work begins on site, our team will be providing the community with updates like this one every other week, which will include notices of any upcoming activities for the week following and will be posted to our website.

Visit our website to review previous updates, to find construction-related contact information, FAQs, and subscribe to these emails.

Email us at: 1170and1200hancock@foxrockproperties.com
For construction-related questions or concerns, call: 617-347-1765
For project updates or general inquiries, call: 617-829-2719

Thank you,
The FoxRock Properties Thave no