Construction Update:

  • Site work expected in May:
  • Removal of structural debris and foundations
  • Prepare sites for the start of foundations
  • Throughout construction, there may be intermittent lane reductions or street closures around the project to complete underground utility improvements. All road work will be coordinated with the City and advance notice will be sent out to neighbors ahead of the road work.

 

1200 Hancock Street

  • Demolition of the main structure has begun and is expected to be complete in the coming days
  • Demolition debris and foundation removal will occur over the next few weeks.
  • Overhead temporary sidewalk protection is being installed

 

1170 Hancock Street

  • Selective interior demolition is nearing completion
  • Preparing the site to start foundations by the end of May
  • Demolition of 18 Russell Park is expected to begin in May

 

We continue to have supervision at the property and encourage anyone to reach out to us or our construction team with questions, concerns, or comments.

———-

Project Timeline

March/April 2022: Demolition of 1200 Hancock St. is expected to begin
Early Spring 2022: Excavation and foundations at both buildings ongoing through the summer of 2022
Early 2024: The project is expected to be complete

———-

Once work begins on site, our team will be providing the community with updates like this one every other week, which will include notices of any upcoming activities for the week following and will be posted to our website.

Visit our website to review previous updates, to find construction-related contact information, FAQs, and subscribe to these emails.

Email us at: 1170and1200hancock@foxrockproperties.com
For construction-related questions or concerns, call: 617-347-1765
For project updates or general inquiries, call: 617-829-2719

Thank you,
The FoxRock Properties Team