Dear Neighbors –

 

Construction Update:

Russell Park is open to one-way vehicle and pedestrian traffic. It is expected that Russell Park will fully open to two-way traffic in late May.

 

1200 Hancock Street 

 

  • Storefront installation is substantially complete
  • Siding installation will continue through February into March
  • Finish installation on residential units is ongoing through March into early April
  • Interior mechanical, electrical, and plumbing rough in the lobby and upper garage level will continue through February
  • Retail tenant fit out construction is ongoing

 

We continue to have supervision at the property and encourage anyone to reach out to us or our construction team with questions, concerns, or comments.